Journal of ZheJiang University (Engineering Science)  2026, Vol. 60 Issue (9): 2007-2014    DOI: 10.3785/j.issn.1008-973X.2026.09.018
    
Impact of newly built bridge pile foundation construction on existing underground utility
Qi GUO1(),Huaping WAN1,*(),Jianghai LIN2,Zhifeng LV2
1. College of Civil Engineering and Architecture, Zhejiang University, Hangzhou 310058, China
2. China Construction Seventh Engineering Division Limited Company, Zhengzhou 450003, China
Download: HTML     PDF(3070KB) HTML
Export: BibTeX | EndNote (RIS)      

Abstract  

A systematic assessment method combining three-dimensional finite element model with global sensitivity analysis was proposed to analyze the multi-factor coupling mechanism involved in the impact of new bridge pile construction on adjacent existing underground utility. A 3D finite element model of the pile-soil-tunnel system was established based on a bridge project adjacent to underground utility in Wenzhou. The Morris method was employed to systematically quantify the influence degree, nonlinear characteristics, and the dynamic evolution of the dominance hierarchy of key factors, including the pile-tunnel clear distance, pile geometry parameters, and dewatering depth during construction. Results indicate that settlement is the predominant displacement response of the underground facility under all conditions. The pile-tunnel clear distance is the dominant factor controlling displacement when the clear distance is less than 3 times the tunnel diameter. The influence of the pile geometric parameter rises significantly and becomes the dominant factor as the clear distance increases. The pile length exhibits the strongest nonlinear effect among all parameters, and the influence of the pile length on displacement reaches a maximum when the pile tip is at a depth comparable to that of the underground facility.



Key wordsbridge project      pile construction      underground facility      sensitivity analysis      Morris method     
Received: 29 October 2025      Published: 20 July 2026
CLC:  TU 473  
Fund:  国家自然科学基金资助项目(52561145240);中央高校基本科研业务费专项资金资助项目(226-2025-00159).
Corresponding Authors: Huaping WAN     E-mail: qi_guo@zju.edu.cn;hpwan@zju.edu.cn
Cite this article:

Qi GUO,Huaping WAN,Jianghai LIN,Zhifeng LV. Impact of newly built bridge pile foundation construction on existing underground utility. Journal of ZheJiang University (Engineering Science), 2026, 60(9): 2007-2014.

URL:

https://www.zjujournals.com/eng/10.3785/j.issn.1008-973X.2026.09.018     OR     https://www.zjujournals.com/eng/Y2026/V60/I9/2007


新建桥梁桩基施工对既有地下设施的影响

为了分析新建桥梁桩基施工对邻近既有地下设施影响的多因素耦合作用机制,提出结合三维有限元模型与全局敏感性分析的系统评估方法. 以温州某邻近地下设施的桥梁工程为背景,建立桩-土-隧三维有限元模型,引入Morris方法,系统量化了桩-隧净距、桩基几何参数及施工过程中降水高度等关键因素的影响程度、非线性特性及其主次关系随距离的动态演变规律. 结果表明,在所有工况下,沉降均是地下设施的主要位移响应形式. 当桩-隧净距小于3倍隧道直径时,桩-隧净距是控制位移的主导因素. 随着桩-隧净距的增大,桩基几何尺寸的影响显著上升并成为主导因素. 各参数中,桩长对地下设施位移的影响呈现最强的非线性效应,且在桩尖位置与地下设施埋深相当时达到最大.


关键词: 桥梁工程,  桩基施工,  地下设施,  敏感性分析,  Morris法 
Fig.1 Location of bridge and underground utility
土层名称排水类型$ {\gamma }_{{\mathrm{sat}}} $/(kN·m?2)$ E_{50}^{\text{ref}} $/(kN·m?2)$ E_{\mathrm{oed}}^{\text{ref}} $/(kN·m?2)$ E_{\mathrm{ur}}^{\text{ref}} $/(kN·m?2)$ \nu _{{\mathrm{ur}}} $$ {c}^{\text{ref}} $/(kN·m?2)$ \varphi /({^{\circ}}) $$ \psi /({^{\circ}}) $$ {R}_{\text{inter}} $
杂填土排水20.0$ 2.2\times {10}^{4} $$ 2.2\times {10}^{4} $$ 6.60\times {10}^{4} $0.2013000.65
淤泥夹粉砂不排水18.0$ 0.9\times {10}^{4} $$ 0.9\times {10}^{4} $$ 2.70\times {10}^{4} $0.20102400.55
淤泥不排水17.0$ 1.0\times {10}^{4} $$ 1.0\times {10}^{4} $$ 3.00\times {10}^{4} $0.2061800.50
淤泥质黏土不排水17.5$ 0.5\times {10}^{4} $$ 0.5\times {10}^{4} $$ 1.50\times {10}^{4} $0.20131500.60
黏土不排水19.0$ 1.25\times {10}^{4} $$ 1.25\times {10}^{4} $$ 3.75\times {10}^{4} $0.20221900.65
卵石排水19.5$ 4.0\times {10}^{5} $$ 4.0\times {10}^{5} $$ 1.20\times {10}^{6} $0.1513880.70
粉砂排水20.0$ 0.9\times {10}^{4} $$ 0.9\times {10}^{4} $$ 2.55\times {10}^{4} $0.1823000.70
Tab.1 Parameter of hardening soil model
Fig.2 Finite element model of pile-soil-tunnel
Fig.3 Variation of pile shaft friction resistance with depth
Fig.4 Schematic of garlic-shaped shaft resistance distribution decomposition
Fig.5 Result of pile foundation settlement
参数$ L $$ D $$ S $$ W $
水平19.6250.9306.29.625
水平226.951.3959.326.95
水平342.351.86012.442.35
水平457.752.32515.557.75
Tab.2 Parameter value at four levels$ (S \lt 3d) $ m
参数$ L $$ D $$ S $$ W $
水平19.6250.93018.69.625
水平226.951.39521.726.95
水平342.351.86024.842.35
水平457.752.32527.957.75
Tab.3 Parameter value at four levels$ (S\geqslant 3d) $ m
Fig.6 Influence of parameters on tunnel displacement $ (S \lt 3d) $
Fig.7 Influence of parameters on tunnel displacement$ (S\geqslant 3d) $
Fig.8 Curve of maximum tunnel displacement under different pile length
Fig.9 Curve of maximum tunnel displacement under different pile diameter
Fig.10 Curve of maximum tunnel displacement under different horizontal pile-tunnel clear distance
Fig.11 Curve of maximum tunnel displacement under different dewatering condition
[1]   丁智, 张霄, 周联英, 等 近距离桥桩与地铁隧道相互影响研究及展望[J]. 浙江大学学报: 工学版, 2018, 52 (10): 1943- 1953
DING Zhi, ZHANG Xiao, ZHOU Lianying, et al Research and prospect of interaction between close bridge pile and metro tunnel[J]. Journal of Zhejiang University: Engineering Science, 2018, 52 (10): 1943- 1953
[2]   徐云福, 王立峰 近邻桩基施工对城市地铁隧道的影响分析[J]. 岩土力学, 2015, 36 (Suppl.2): 577- 582
XU Yunfu, WANG Lifeng Analysis of effects on city metro tunnel due to adjacent pile foundation construction[J]. Rock and Soil Mechanics, 2015, 36 (Suppl.2): 577- 582
[3]   王磊, 俞峰, 潘静杰 敞口管型桩压入对既有受荷桩基承载性状影响[J]. 浙江大学学报: 工学版, 2021, 55 (12): 2243- 2251
WANG Lei, YU Feng, PAN Jingjie Influence of jacking open-ended tubular piles on bearing behavior of existing in-service piles[J]. Journal of Zhejiang University: Engineering Science, 2021, 55 (12): 2243- 2251
doi: 10.3785/j.issn.1008-973X.2021.12.003
[4]   王超, 朱春洲, 邹金锋, 等 盾构隧道近接斜交侧穿桥梁桩基变形计算方法[J]. 浙江大学学报: 工学版, 2024, 58 (3): 557- 569
WANG Chao, ZHU Chunzhou, ZOU Jinfeng, et al Calculation approach for deformation of adjacent pile foundation caused by diagonal intersection with side penetration construction of shield tunnel[J]. Journal of Zhejiang University: Engineering Science, 2024, 58 (3): 557- 569
doi: 10.3785/j.issn.1008-973X.2024.03.013
[5]   杨文东, 吴洋, 王智德, 等 隧道开挖对既有桩基影响分区的试验研究[J]. 现代隧道技术, 2024, 61 (6): 200- 208
YANG Wendong, WU Yang, WANG Zhide, et al Experimental study on the influence zoning on existing pile foundations induced by tunnelling[J]. Modern Tunnelling Technology, 2024, 61 (6): 200- 208
doi: 10.13807/j.cnki.mtt.2024.06.022
[6]   丁智, 张霄 桩基施工对邻近既有地铁隧道影响的数值分析[J]. 中南大学学报: 自然科学版, 2019, 50 (2): 390- 399
DING Zhi, ZHANG Xiao Numerical analysis of influence of pile foundation construction on adjacent metro tunnel[J]. Journal of Central South University: Science and Technology, 2019, 50 (2): 390- 399
[7]   钱叶琳, 张振华, 崔文天, 等 考虑地层蠕变效应的桥梁桩基施工对邻近运营地铁隧道的影响[J]. 科学技术与工程, 2024, 24 (9): 3781- 3788
QIAN Yelin, ZHANG Zhenhua, CUI Wentian, et al Influence of the construction of the bridge pile foundation on the adjacent operating subway tunnel considering creep characteristics of stratum[J]. Science Technology and Engineering, 2024, 24 (9): 3781- 3788
doi: 10.12404/j.issn.1671-1815.2301925
[8]   杨敏, 靳军伟 桩基础与既有地铁隧道相互影响的研究进展[J]. 建筑结构学报, 2016, 37 (8): 90- 100
YANG Min, JIN Junwei Research progress on interaction of pile foundation with nearby existing subway tunnel[J]. Journal of Building Structures, 2016, 37 (8): 90- 100
[9]   陈大平, 明升亮, 汪泽楷, 等 桩基施工对邻近地铁扰动效应的数值模拟研究[J]. 建筑结构, 2023, 53 (Suppl. 2): 2456- 2461
CHEN Daping, MING Shengliang, WANG Zekai, et al Study on numerical simulation of disturbance effect of pile foundation construction on adjacent subway[J]. Building Structure, 2023, 53 (Suppl. 2): 2456- 2461
[10]   陈福江, 段蓉蒨, 张鑫, 等 近距离桩基施工对既有盾构隧道的振动影响分析[J]. 现代隧道技术, 2023, 60 (1): 140- 148
CHEN Fujiang, DUAN Rongqian, ZHANG Xin, et al Analysis on vibration influence of the construction of short-distance pile foundation on existing shield tunnels[J]. Modern Tunnelling Technology, 2023, 60 (1): 140- 148
[11]   刘爱荣, 张俊平, 禹奇才, 等 桩-土-结构相互作用对大跨度连续刚架钢桁拱桥地震响应影响研究[J]. 桥梁建设, 2007, 37 (1): 25- 27
LIU Airong, ZHANG Junping, YU Qicai, et al Study of influences of pile-soil-structure interaction on seismic response of long span continuous rigid-frame and steel truss arch bridge[J]. Bridge Construction, 2007, 37 (1): 25- 27
doi: 10.3969/j.issn.1003-4722.2007.01.006
[12]   罗跃, 叶淑君, 吴吉春, 等 地面沉降模型的参数全局敏感性[J]. 浙江大学学报: 工学版, 2018, 52 (10): 2007- 2013
LUO Yue, YE Shujun, WU Jichun, et al Global sensitivity analysis of parameters in land subsidence model[J]. Journal of Zhejiang University: Engineering Science, 2018, 52 (10): 2007- 2013
doi: 10.3785/j.issn.1008-973X.2018.10.021
[13]   楼恺俊, 俞峰, 夏唐代, 等 黏土中地下连续墙支护结构的稳定性分析[J]. 浙江大学学报: 工学版, 2020, 54 (9): 1697- 1705
LOU Kaijun, YU Feng, XIA Tangdai, et al Stability analysis of diaphragm wall retained structure in clay[J]. Journal of Zhejiang University: Engineering Science, 2020, 54 (9): 1697- 1705
doi: 10.3785/j.issn.1008-973X.2020.09.005
[14]   MORRIS M D Factorial sampling plans for preliminary computational experiments[J]. Technometrics, 1991, 33 (2): 161- 174
doi: 10.1080/00401706.1991.10484804
[15]   周鼎文, 韩磊, 应宏伟, 等 分隔型基坑施工对邻近地层及隧道位移的影响[J]. 浙江大学学报: 工学版, 2025, 59 (5): 1072- 1082
ZHOU Dingwen, HAN Lei, YING Hongwei, et al Effect of segregated pit construction on displacement of adjacent strata and tunnel[J]. Journal of Zhejiang University: Engineering Science, 2025, 59 (5): 1072- 1082
[16]   万华平, 卫志成, 苏雷, 等 考虑桩径效应的桥梁结构地震风险分析[J]. 振动与冲击, 2021, 40 (15): 224- 231
WAN Huaping, WEI Zhicheng, SU Lei, et al Seismic risk analysis of bridge structure considering pile diameter effect[J]. Journal of Vibration and Shock, 2021, 40 (15): 224- 231
doi: 10.13465/j.cnki.jvs.2021.15.028
[17]   张中杰, 周赫宸, 顾晓强, 等 天津某超深地铁基坑变形分析与小应变硬化参数取值[J]. 浙江大学学报: 工学版, 2025, 59 (12): 2593- 2603
ZHANG Zhongjie, ZHOU Hechen, GU Xiaoqiang, et al Deformation analysis and parameter determination of hardening soil model with small strain of an ultra-deep subway excavation in Tianjin[J]. Journal of Zhejiang University: Engineering Science, 2025, 59 (12): 2593- 2603
[18]   王卫东, 王浩然, 徐中华 基坑开挖数值分析中土体硬化模型参数的试验研究[J]. 岩土力学, 2012, 33 (8): 2283- 2290
WANG Weidong, WANG Haoran, XU Zhonghua Experimental study of parameters of hardening soil model for numerical analysis of excavations of foundation pits[J]. Rock and Soil Mechanics, 2012, 33 (8): 2283- 2290
doi: 10.3969/j.issn.1000-7598.2012.08.008
[19]   张超, 杨龙才, 黄大维, 等 钢套管施工对地铁隧道影响分析及变形控制研究[J]. 岩石力学与工程学报, 2013, (Suppl.2): 3584- 3591
ZHANG Chao, YANG Longcai, HUANG Dawei, et al Effect of steel casing construction on metro tunnel and deformation control[J]. Chinese Journal of Rock Mechanics and Engineering, 2013, (Suppl.2): 3584- 3591
[20]   MINDLIN R D Force at a point in the interior of a semi-infinite solid[J]. Physics, 1936, 7 (5): 195- 202
doi: 10.1063/1.1745385
[21]   刘金砺, 秋仁东, 高文生, 等 关于长桩超长桩桩基沉降计算问题[J]. 岩土工程学报, 2011, 33 (Suppl.2): 38- 42
LIU Jinli, QIU Rendong, GAO Wensheng, et al Settlement calculation of foundation with long and super-long piles[J]. Chinese Journal of Geotechnical Engineering, 2011, 33 (Suppl.2): 38- 42
[22]   刘金砺, 秋仁东, 邱明兵, 等 不同条件下桩侧阻力端阻力性状及侧阻力分布概化与应用[J]. 岩土工程学报, 2014, 36 (11): 1953- 1970
LIU Jinli, QIU Rendong, QIU Mingbing, et al Behaviors of shaft resistance and tip resistance of piles under different conditions and conceptualization and application of distribution of shaft resistance[J]. Chinese Journal of Geotechnical Engineering, 2014, 36 (11): 1953- 1970
[23]   高大峰, 赵俊逸, 龚大能, 等 桩基础荷载对近接隧道影响的数值分析[J]. 自然灾害学报, 2019, 28 (5): 39- 47
GAO Dafeng, ZHAO Junyi, GONG Daneng, et al Numerical analysis of influence of pile foundation loading on approaching tunnel[J]. Journal of Natural Disasters, 2019, 28 (5): 39- 47
doi: 10.13577/j.jnd.2019.0505
[1] Kaiwen ZHANG,Xueni WANG,zhenyue MA,Jinjian ZHANG,Leike ZHANG,Lijun CHEN. Sensitivity analysis of hydroelectric unit parameters controlled by magnetorheological fluid dampers[J]. Journal of ZheJiang University (Engineering Science), 2026, 60(5): 1037-1046.
[2] Xiao-yan CAO,Min YU,Jin ZHOU,Yun-zhi WANG. Multi-objective optimization design of adjustable rotary fluid damper parameter[J]. Journal of ZheJiang University (Engineering Science), 2023, 57(7): 1439-1449.
[3] Ying LI,Guan-xiong WANG,Wei YAN,Ying-ge ZHAO,Chong-lei MA. Improved sparse grid collocation method for uncertainty quantification of EIT conductivity distribution[J]. Journal of ZheJiang University (Engineering Science), 2022, 56(3): 613-621.
[4] Jia-yi SHEN,Meng KU,Li-zhong WANG. Stability analyses of submarine slopes based on shear band propagation method[J]. Journal of ZheJiang University (Engineering Science), 2021, 55(7): 1299-1307.
[5] Xiu-fen ZHANG,Yun-fei GAO. Multi-dimensional hierarchical remanufacturability evaluation method for end-of-life mechanical parts[J]. Journal of ZheJiang University (Engineering Science), 2020, 54(5): 954-962.
[6] Teng-yi HUANG,Jin ZHOU,Yan XU,Fan-xu MENG. Modeling of MR damper based on multi-field coupling analysis and influence of structural parameters[J]. Journal of ZheJiang University (Engineering Science), 2020, 54(10): 2001-2008.
[7] Feng CHENG,Dong ZHANG,Shuo TANG. Aerodynamics/propulsion coupled modeling and analysis of hypersonic vehicle within wide speed range[J]. Journal of ZheJiang University (Engineering Science), 2019, 53(5): 1006-1018.
[8] Jin ZHOU,Tian-yu GAO,Yi CHEN,Hong-hao XI. Model updating of dual-rotor decanter centrifuge with dynamic test[J]. Journal of ZheJiang University (Engineering Science), 2019, 53(2): 241-249.
[9] REN Song, OUYANG Xun, WU Jian-xun, CHEN Fan, WANG Liang, CHEN Jie. Elastic-swelling analytical model of anhydrite rock considering time-dependent effect[J]. Journal of ZheJiang University (Engineering Science), 2018, 52(5): 896-905.
[10] BAO Teng-fei, LI Jian-ming, ZHAO Jin-lei. Strain transfer analysis between embedded plastic optical fibers and concretes[J]. Journal of ZheJiang University (Engineering Science), 2018, 52(12): 2342-2348.
[11] LUO Yue, YE Shu-jun, WU Ji-chun, ZHANG Yan-hong, JIAO Xun, WANG Han-mei. Global sensitivity analysis of parameters in land subsidence model[J]. Journal of ZheJiang University (Engineering Science), 2018, 52(10): 2007-2013.
[12] FU Jian-xin, SONG Wei-dong, TAN Yu-ye. Influence degree analysis of rock mass' mechanical parameters on roadway's deformation characteristics[J]. Journal of ZheJiang University (Engineering Science), 2017, 51(12): 2365-2372.
[13] LIU Kai, CAO Yi, ZHOU Rui, GE Shu-yi, DING Rui. Modeling and optimizing of one-translational and two-rotational LEMs flexure hinge[J]. Journal of ZheJiang University (Engineering Science), 2017, 51(12): 2399-2407.
[14] HE Hai bin, YAO Dong wei, WU Feng. Construction and optimization of kinetic mechanism for alternative fuel of COG[J]. Journal of ZheJiang University (Engineering Science), 2016, 50(10): 1841-1848.
[15] YIN Jiao-mei, ZHAO Xin-yue, ZHANG Shu-you. Method for designing parts structure to resist harsh environments considering sobol defects sensitivity[J]. Journal of ZheJiang University (Engineering Science), 2015, 49(8): 1487-1494.