Please wait a minute...
J4  2011, Vol. 45 Issue (10): 1791-1798    DOI: 10.3785/j.issn.1008-973X.2011.10.016
能源与机械工程     
基于风险检验技术的电站锅炉过热器评定方法
刘富君1, 孔帅1, 凌张伟1, 郑慕林1, 钱岳强1,
金南辉1, 王强2, 李翔3
1. 浙江省特种设备检验研究院,浙江 杭州 310020;2.中国计量学院 质量与安全工程学院,浙江 杭州 310018;
3.浙江大学 化工机械研究所,浙江 杭州 310020
Assessment methodology of power station boiler superheater based on
risk-based inspection technology
LIU Fu-jun1, KONG Shuai1, LING Zhang-wei1, ZHENG Mu-lin1,
QIAN Yue-qiang1, JIN Nan-hui1, WANG Qiang2, LI Xiang3
1. Zhejiang Provincial Special Equipment Inspection and Research Institute, Hangzhou 310020, China;
2. School of Quality and Safety Engineering, China Jiliang University, Hangzhou 310018, China;
3. Institute of Chemical Machinery Engineering, Zhejiang University, Hangzhou 310020, China
 全文: PDF  HTML
摘要:

为了科学评价电站锅炉过热器的风险状况,制定合理的管理和维护策略,减少非计划停炉,研究基于风险检验(RBI)技术的过热器风险评定方法.研究过热器炉管的失效机理,建立适用于过热器炉管的高温烟气冲蚀因子和高温蠕变因子计算方法;结合我国超期服役、炉管材料初始缺陷等情况,提出基于剩余寿命参量的失效可能性修正系数;进一步确定合理的经济损失法来计算炉管失效后果,建立失效后果等级划分准则.通过对某末级过热器炉管失效的可能性和失效后果进行定量分析和计算,评定了炉管风险等级,制定了合理的管理和维护策略.

Abstract:

The risk assessment methodology based on risk-based inspection (RBI) was analyzed in order to evaluate the risk situation of the power station boiler superheater to establish the reasonable management, and maintenance strategy and reduce the non-plan shutdowns. The failure mechanism of power station boiler was analyzed, and the creep damage factor computing technical module and high-temperature smoke erosion thinning technical module for power station boiler tubes were conducted. The failure probability correction factor was presented based on the remaining life, considering China’s national condition, including the extended service and initial material defects etc. Moreover, the proper financial risk calculation method was established to assess the risk consequence, and the grade distinguish rule was established. The risk level was evaluated through the failure possibility and consequence quantitative analysis and calculation of a superheater, and the reasonable management and maintenance strategy was established.

出版日期: 2011-10-01
:  TK 228  
基金资助:

国家质量监督检验检疫总局科技计划资助项目(2009QK176); 浙江省质量技术监督局重大科技资助项目(20090106).

作者简介: 刘富君(1976—),男,博士,高工,从事特种设备设计理论、结构强度、安全监控、数值模拟、全寿命预测、风险评估及无损检验检测技术等研究.E-mail:lfj_dq@126.com
服务  
把本文推荐给朋友
加入引用管理器
E-mail Alert
作者相关文章  

引用本文:

刘富君, 孔帅, 凌张伟, 郑慕林, 钱岳强, 金南辉, 王强, 李翔. 基于风险检验技术的电站锅炉过热器评定方法[J]. J4, 2011, 45(10): 1791-1798.

LIU Fu-jun, KONG Shuai, LING Zhang-wei, ZHENG Mu-lin, QIAN Yue-qiang,JIN Nan-hui. Assessment methodology of power station boiler superheater based on
risk-based inspection technology. J4, 2011, 45(10): 1791-1798.

链接本文:

https://www.zjujournals.com/eng/CN/10.3785/j.issn.1008-973X.2011.10.016        https://www.zjujournals.com/eng/CN/Y2011/V45/I10/1791

[1] 孟祥泽,韩建慧.电站锅炉压力容器事故案例分析与预防[M].北京:中国水利水电出版社,2007: 14-71.
[2] American Petroleum Institute. Riskbased inspection base resource document, API 581[S]. 1st ed. Washington:American Petroleum Institute, 2000.
[3] American Petroleum Institute. Riskbased inspection, API 580 [S]. Washington:American Petroleum Institute, 2002.
[4] 邵松伟.RBI技术在电站锅炉系统中的应用研究[D].兰州:兰州理工大学,2009.
SHAO Songwei. Research on the application of RBI technology for the boiler system in power plant [D]. Lanzhou: Lanzhou University of Technology, 2009.
[5] 郑世津.国外锅炉炉管泄漏防治工作发展综述及启示[J].电站系统工程,2004, 20(3): 11-14.
ZHENG Shijin. Development of preventing boiler tube failure BTF) at abroad and revelation [J]. Power System Engineering, 2004, 20(3): 11-14.
[6] 杨震.电站锅炉炉管失效机理和提高可靠性的措施[J]. 锅炉技术, 2001, 32(12): 1-7.
YANG Zhen. Mechanism for utility boiler tube failure and measures to improve reliability [J]. Boiler Technology, 2001, 32(12): 1-7.
[7] 纪冬梅,施睿贇,杨森.亚临界锅炉后屏过热器12Cr1MoV炉管的剩余寿命预测[J].压力容器,2008, 25(9): 11-14.
JI Dongmei, SHI Ruiyun, YANG Sen. Life prediction of 12Cr1MoV rear platen superheat boiler tube in a power plant [J]. Pressure Vessel Technology, 2008, 25(9): 11-14.
[8] 王小辉,刘钧泉.一段转化炉高温炉管剩余寿命评估[J].石油化工设备,2008, 37(2): 73-77.
WANG Xiaohui, LIU Junquan. Residual life evaluation of high temperature tubes in primary reformer [J]. PetroChemical Equipment, 2008, 37(2): 73-77.

[9] GIRIBONE R, VALETTE B. Principles of failure probability assessment (PoF) [J]. International Journal of Pressure Vessels and Piping, 2004(7): 797-806.
[10] HARALD K. Conditional firstorder secondmoment method and its application to the quantification of uncertainty in groundwater modeling [J]. Water Resources Research, 2002, 38(4): 1-14.
[11] 傅敏,岳增武,雒利勇,等.锅炉省煤器的飞灰磨损状态及材料耐磨性能浅析[J].山东电力技术, 2000(5): 14-16.
FU Min, YUE Zengwu, LUO Liyong, et al. Erosion states on the boiler economizer by fly ash and the erosion resistant ability of materials [J]. Shandong Electric Power, 2000(5): 14-16.
[12] 岑可法,樊建人,池作和,等.锅炉和热交换器的积灰、结渣、磨损和腐蚀的防止原理与计算[M].北京:科学出版社, 1994: 424.
[13] American Petroleum Institute. Calculation of heater tube thickness in petroleum refineries. API 530 [S]. 5th ed. Washington: API, 2003.
[14] SANTOSH A, VINODA G, SHRIVASTAVA O P. Reliability analysis of pipelines carrying H2S for risk based inspection of heavy water plants [J]. Reliability Engineering and System Safety, 2006, 91(2): 163-170.
[15] SCHRODER H C, KAUER R. Regulatory requirements related to riskbased inspection and maintenance [J]. International Journal of Pressure Vessels and Piping, 2004, 81(10/11): 847-854.
[16] STIRLING A. Risk at a turning point [J]. Journal of Environmental Medicine, 1999, 1(2): 119-126.
[17] 杨卫娟,周志军,刘茂省,等.锅炉低NOx燃烧中的三次风运行优化[J].浙江大学学报:工学版, 2008, 42(7): 1227-1230, 1270.
YANG Weijuan, ZHOU Zhijun, LIU Maosheng, et al. Tertiary air operation optimization aiming at low NOx combustion in boiler [J]. Journal of Zhejiang University:Engineering Science, 2008, 42(7): 1227-1230, 1270.
[18] 郭雷.电站锅炉冲蚀磨损机理及材料防磨性能的试验研究[D].太原:太原理工大学,2007.
GUO Lei. An experimental study on the erosion mechanism in power station and the antierosion performance of materials [D]. Taiyuan: Taiyuan University of Technology, 2007.