Constant-force jack unloading method for removing temporary supports from large-span steel roof" />
Constant-force jack unloading method for removing temporary supports from large-span steel roof" />
Constant-force jack unloading method for removing temporary supports from large-span steel roof" />
大跨度屋盖钢结构拆撑过程恒力千斤顶卸载法
Constant-force jack unloading method for removing temporary supports from large-span steel roof
GUO Xiao-nong1, YANG Shang-fei1, LUO Yong-feng1, QIU Li-qiu1, YU Zheng-hua2, ZHENG Xiang-jie2
1. Department of Building Engineering, Tongji University, Shanghai 200092, China;2. Shanghai Mechanized Construction Group Limited Company, Shanghai 200439, China
In view of removing temporary supports from the large span steel structural roof, a new unloading method which was called constant-force jack unloading method was proposed. The constant jack with COMBIN37 element of ANSYS was simulated. Then a classic numerical analysis model was constructed, and was analyzed respectively by support displacement method, the equivalent rod end displacement method, jack element method, constraint equation method and constant-force jack unloading method. The analysis results show that compared with the traditional displacement-control method, the constant-force jack unloading method can effectively control the force change of the jack. The internal force and deflection of the structure were more efficiently controlled. The constant-force jack unloading method is especially applicable to the structure with large stiffness.