Risk transfer process in urban comprehensive corridor PPP project based on complex network model |
Lin YANG1( ),Jia-jun WANG2 |
1. School of Civil Engineering, Wuhan University, Wuhan 430072, China 2. Central and Southern Municipal Engineering Design and Research Institute, Wuhan 430014, China |
|
|
Abstract From the perspective of complex network, the case analysis method was used to identify 38 risk elements of the urban comprehensive corridor PPP projects primarily; the 38 risk elements were used as network points, and the relationship between risk elements was taken as network edges to construct the complex network model. By analyzing three kinds of complex network parameters, the risk transfer process of the urban comprehensive corridor PPP projects was expounded. Based on the case study of urban comprehensive corridor PPP project in Shiyan city, eight core factors affecting risk transmission were found, which provided the basis for decision makers to control and prevent risks. Results show that the realization of risk prevention and control needs to control the direct risk and cut off the transmission path of indirect risk, thus to guide the risk transmission effectively by controlling the core factors of risk. The breakthrough of risk transmission of complex projects is found in theory, and the effective risk control mode of complex projects is explored in practice.
|
Received: 19 September 2019
Published: 22 September 2020
|
|
基于复杂网络模型的城市综合管廊PPP项目风险传递过程研究
从复杂网络视角出发,利用案例分析法识别出城市综合管廊PPP项目的38个风险要素,将风险要素作为网络点,并将风险要素之间的关系作为网络边,构建复杂网络模型;通过分析3类复杂网络参数,阐明城市综合管廊PPP项目的风险传递过程;基于十堰市城市综合管廊PPP项目的实例,找到8个影响风险传递的核心因素,为决策者提供风险控制和防范的依据. 研究表明:实现风险防控需要控制直接风险并切断间接引发风险的传递路径,通过控制风险核心因素的方式有效引导风险传递. 以上研究从理论上发现了复杂项目风险传递的突破口,在实践上探索了行之有效的复杂项目风险控制模式.
关键词:
城市综合管廊,
公私合作(PPP)项目,
复杂网络,
风险识别,
风险传递,
案例分析法
|
|
[1] |
薛学斌, 殷吉彦, 周洲, 等 城市综合管廊相关问题探讨[J]. 给水排水, 2017, 53 (1): 137- 142 XUE Xue-bin, YIN Ji-yan, ZHOU Zhou. et al Discussion on related issues of urban integrated pipe gallery[J]. Water Supply and Drainage, 2017, 53 (1): 137- 142
doi: 10.3969/j.issn.1002-8471.2017.01.027
|
|
|
[2] |
段泳仲 城市地下综合管廊PPP项目风险管理研究[J]. 中国集体经济, 2019, 593 (9): 51- 52 DUAN Yong-zhong Research on risk management of PPP project in urban underground integrated pipe gallery[J]. China Collective Economy, 2019, 593 (9): 51- 52
doi: 10.3969/j.issn.1008-1283.2019.9.023
|
|
|
[3] |
安玉华, 蔡国艳 城市地下综合管廊PPP项目现存问题及对策研究[J]. 价值工程, 2018, 37 (20): 90- 92 AN Yu-hua, CAI Guo-yan Study on existing problems and countermeasures of PPP project of urban underground utility tunnel[J]. Value Engineering, 2018, 37 (20): 90- 92
|
|
|
[4] |
贾康, 满莉, 费太安, 等 城市地下综合管廊投资回报机制研究[J]. 经济研究参考, 2018, 2869 (21): 5- 27 JIA Kang, MAN Li, FEI Tai-an, et al Study on investment return mechanism of urban underground comprehensive pipeline[J]. Review of Economic Research, 2018, 2869 (21): 5- 27
|
|
|
[5] |
吴思材, 郭汉丁, 郑悦红, 等 公平视域下PPP项目收益分配[J]. 土木工程与管理学报, 2018, 35 (2): 185- 192 WU Si-cai, GUO Han-ding, ZHENG Yue-Hong, et al Study on investment return mechanism of urban underground comprehensive pipeline[J]. Journal of Civil Engineering and Management, 2018, 35 (2): 185- 192
|
|
|
[6] |
赵辉, 邱玮婷, 王楠, 等 城市轨道交通PPP项目运作方式选择[J]. 土木工程与管理学报, 2018, 35 (4): 42- 49 ZHAO Hui; QIU Wei-ting; WANG Nan, et al Choice of PPP operation mode of urban rail transit project[J]. Journal of Civil Engineering and Management, 2018, 35 (4): 42- 49
|
|
|
[7] |
王建波, 刘芳梦 城市轨道交通PPP项目全生命周期绩效评价[J]. 土木工程与管理学报, 2018, 35 (6): 23- 29 WANG Jian-bo, LIU fang-meng Evaluation of total life cycle performance of urban rail transit public private partnerships project[J]. Journal of Civil Engineering and Management, 2018, 35 (6): 23- 29
doi: 10.3969/j.issn.2095-0985.2018.06.004
|
|
|
[8] |
王军, 陈欣盛, 李少龙, 等 城市地下综合管廊建设及运营现状[J]. 土木工程与管理学报, 2018, 35 (2): 105- 113 WANG Jun, CHEN Xin-sheng, LI Shao-long, et al About construction and operation present situation of utility tunnel in urban[J]. Journal of Civil Engineering and Management, 2018, 35 (2): 105- 113
|
|
|
[9] |
李芊, 王莹莹 城市地下综合管廊项目PPP模式选择[J]. 隧道建设, 2017, 37 (9): 1076- 1082 LI Qian, WANG Ying-ying Selection of public private partnership (PPP) modes for urban underground utility tunnels[J]. Tunnel Construction, 2017, 37 (9): 1076- 1082
doi: 10.3973/j.issn.1672-741X.2017.09.003
|
|
|
[10] |
陈倬 PPP模式助力综合管廊建设: 理论、政策与实践[J]. 武汉金融, 2017, (4): 22- 25 CHEN Xie PPP model to help the construction of integrated management corridor: theory, policy and practice[J]. Wuhan Finance, 2017, (4): 22- 25
|
|
|
[11] |
李艳艳, 郭伟 城市地下综合管廊PPP项目交易结构设计[J]. 地下空间与工程学报, 2017, 13 (5): 1150- 1156 LI Yan-yan, GUO Wei Design of transaction structure for PPP project of the urban underground military utility tunnel[J]. Chinese Journal of underground space and engineering, 2017, 13 (5): 1150- 1156
|
|
|
[12] |
LEWIS M K, GRIMSEY D The governance of contractual relationships in public private partnerships[J]. Journal of Corporate Citizenship, 2004, 15 (03): 91- 109(19)
|
|
|
[13] |
GRIMSEY D, LEWIS M Evaluating the risks of public private partnerships for infrastructure projects[J]. International Journal of Project Management, 2002, 20 (2): 107- 118
doi: 10.1016/S0263-7863(00)00040-5
|
|
|
[14] |
JOHN E, ISR W Alternate financing strategies for build operate transfer projects[J]. Journal of Construction Engineering and Management, 2003, 129 (2): 205- 213
doi: 10.1061/(ASCE)0733-9364(2003)129:2(205)
|
|
|
[15] |
MOUSAVI S M, EBRAHIMNEJAD S. Risk identification and assessment for build operate transfer projects: a fuzzy multi attribute decision-making model[J]. Expert Systems with Applications, 2010, 37: 575- 586
doi: 10.1016/j.eswa.2009.05.037
|
|
|
[16] |
WIBOWO A , KOCHENDOERFER B . Financial risk analysis of project finance in Indonesian toll roads[J]. Journal of Construction Engineering and Management, 2005, 131 (9): 963- 972
doi: 10.1061/(ASCE)0733-9364(2005)131:9(963)
|
|
|
[17] |
THOMAS A V , KALIDINDI S N , GANESH L S. Modeling and assessment of critical risks in BOT road projects[J]. Construction Management and Economics, 2006, 24 (4): 407- 424
doi: 10.1080/01446190500435275
|
|
|
[18] |
有维宝, 王建波, 张樵民, 等 基于TOPSIS-UT的城市地下综合管廊PPP项目风险分担[J]. 土木工程与管理学报, 2019, 36 (2): 186- 194 WEI Bao, WANG Jian-bo, ZHANG Qiao-min, et al Risk sharing of urban underground utility tunnel PPP project based on topsis-ut[J]. Journal of Civil Engineering and Management, 2019, 36 (2): 186- 194
doi: 10.3969/j.issn.2095-0985.2019.02.029
|
|
|
[19] |
陆仁强, 牛志广, 张宏伟等 城市供水系统风险传播机理模型研究[J]. 自然灾害学报, 2010, 19 (6): 119- 123 LU ren-qiang, NIU Zhi-guang, ZHANG Hong-wei, et al Study on risk transmission mechanism model of urban water supply system[J]. Journal of Natural Disasters, 2010, 19 (6): 119- 123
|
|
|
[20] |
向鹏成, 罗玉苹 重大工程项目建设的社会稳定风险传导机理研究[J]. 世界科技研究与发展, 2014, 36 (04): 420- 425 XIANG Peng-cheng, LUO Yu-ping Researches on conduction mechanism of social stability risk in large-scale engineering projects[J]. World Science and Technology in Research and Development, 2014, 36 (04): 420- 425
doi: 10.3969/j.issn.1006-6055.2014.04.011
|
|
|
[21] |
刘筱驹, 王越 系统集成项目工期风险传递算法及评价控制[J]. 运筹与管理, 2004, 13 (01): 38- 43 LIU Xiao-ju, WANG Yue Evaluation and control of the lead-time risk of the system integration project with risk transfer algorithm[J]. Operations Research and Management Science, 2004, 13 (01): 38- 43
doi: 10.3969/j.issn.1007-3221.2004.01.008
|
|
|
[22] |
任志涛, 武继科 基于结构方程的PPP项目失败关键影响因素分析[J]. 天津城建大学学报, 2017, 23 (1): 60- 65 REN Zhi-tao, WU Ji-ke Analysis on key influence factors of PPP project failure based on structural equation[J]. Journal of Tianjin Chengjian University, 2017, 23 (1): 60- 65
|
|
|
[23] |
段世霞, 朱琼, 侯阳 PPP项目特许价格影响因素的结构方程建模分析[J]. 科技管理研究, 2013, 33 (10): 197- 201 DUAN Shi-xia, ZHU Qiong, HOU Yang Structure equation modeling of influencing factors of contract price of PPP project[J]. Science and Technology Management Research, 2013, 33 (10): 197- 201
doi: 10.3969/j.issn.1000-7695.2013.10.045
|
|
|
[24] |
戴汝为 系统科学及系统复杂性研究[J]. 系统仿真学报, 2002, 14 (11): 1411- 1416 DAI Ru-wei Research on system science and system complexity[J]. Journal of System Simulation, 2002, 14 (11): 1411- 1416
doi: 10.3969/j.issn.1004-731X.2002.11.004
|
|
|
[25] |
潘华, 李永奎 基于社会网络分析视角的大型复杂工程项目组织研究[J]. 科技管理研究, 2013, 33 (20): 214- 217 PAN Hua, LI Yong-kui Study on large and complex engineering projects organization based on social network analysis perspective[J]. Science and Technology Management Research, 2013, 33 (20): 214- 217
doi: 10.3969/j.issn.1000-7695.2013.20.043
|
|
|
[26] |
杨琳 基于社会网络分析法的复杂工程项目组织网络模型构建[J]. 武汉大学学报: 工学版, 2012, 45 (3): 345- 349 YANG Lin Research on organizing network model for complex construction project based on social network analysis[J]. Engineering Journal of Wuhan University, 2012, 45 (3): 345- 349
|
|
|
[27] |
崇丹, 李永奎, 乐云 城市基础设施建设项目群组织网络关系治理研究: 一种网络组织的视角[J]. 软科学, 2012, 26 (2): 13- 19 CHONG dan, LI Yong-kui, LE yun Research on relationship governance in organizational network structure of urban infrastructure construction program: from the perspective of the network theory[J]. Soft Science, 2012, 26 (2): 13- 19
doi: 10.3969/j.issn.1001-8409.2012.02.004
|
|
|
[28] |
杨琳 基于结构洞理论的城市复杂项目群组织优化研究[J]. 数学的实践与认识, 2012, 42 (9): 52- 58 YANG Lin Research on organization optimization for urban complex multi-group based on structure holes[J]. Mathematics in Practice and Theory, 2012, 42 (9): 52- 58
doi: 10.3969/j.issn.1000-0984.2012.09.009
|
|
|
[29] |
王秋菲, 石丹, 常春光 多案例的PPP项目风险分析与防范[J]. 沈阳建筑大学学报: 社会科学版, 2016, 018 (5): 494- 500 WANG qiu-fei, SHI Dan, CHANG Chun-guang Risk analysis and prevention of multi-case PPP projects[J]. Journal of Shenyang Jianzhu University Social Science, 2016, 018 (5): 494- 500
|
|
|
[30] |
张红平, 叶苏东 公私合作(PPP)项目提前终止致因模型研究[J]. 财经论丛, 2017, 222 (7): 104- 112 ZHANG Hong-ping, YE Su-dong A study on the causing factors for early-termination of PPP Projects[J]. Collected Essays on Finance and Economics, 2017, 222 (7): 104- 112
|
|
|
[31] |
王侯亘, 吴兵 基于国内外项目实践的交通基础设施建设PPP模式研究[J]. 科技与创新, 2015, 14 (2): 1- 2 WANG Hou-gen, WU Bing Research on PPP mode of transportation infrastructure construction based on domestic and international project practice[J]. Science and Technology and Innovation, 2015, 14 (2): 1- 2
|
|
|
|
Viewed |
|
|
|
Full text
|
|
|
|
|
Abstract
|
|
|
|
|
Cited |
|
|
|
|
|
Shared |
|
|
|
|
|
Discussed |
|
|
|
|