Life cycle cost assessment for transformer based on incomplete records
TANG Wei, CHEN Ji-xi, WANG Zi-long, ZHENG Jia-jun, GU Xin-jian
Department of Mechanical Engineering, Zhejiang University, Hangzhou 310027, China
Download:   PDF(2659KB) HTML
Export: BibTeX | EndNote (RIS)      

Abstract  

The life cycle cost (LCC) analysis model of transformer based on the incomplete data recording was proposed. The transformer failure cost calculation method based on the product structure tree was analyzed in the case of deficient fault record shortage. The definition of fault product base set (FPBS) was presented. The self-accurate failure cost calculation process model was established, which would be much more precise along with the increasing records. A lifelong cost calculation software for transformer was developed, which supports evaluation of LCC in bidding by using the proposed algorithm and helps enterprises accumulate product data. Then the situation of life cycle data shortage was gradually improved. A practical case study was provided for testing the proposed algorithm. Results show that the LCC model and system is feasible and effective in solving the problem of transformers total cost in whole life evaluation.



Published: 01 January 2014
CLC:  TM 4  
  F 407.61  
Cite this article:

TANG Wei, CHEN Ji-xi, WANG Zi-long, ZHENG Jia-jun, GU Xin-jian. Life cycle cost assessment for transformer based on incomplete records. J4, 2014, 48(1): 42-49.

URL:

http://www.zjujournals.com/eng/10.3785/j.issn.1008-973X.2014.01.007     OR     http://www.zjujournals.com/eng/Y2014/V48/I1/42


基于不完整数据的变压器全生命周期成本

提出基于不完整数据的变压器全生命周期成本(LCC)分析模型,研究在故障记录不完整的情况下,基于产品结构树的变压器故障成本的计算方法.给出故障产品基数集合(FPBS)的定义,建立具有自精确性的零部件故障成本计算过程模型,使LCC分析的精确性随着数据的完善而提高.开发变压器LCC支持系统,应用该算法支持企业招投标中LCC的评估;协助企业累积相关数据,逐步改善产品生命周期数据累积不足的状况.通过实际案例验证表明,该计算模型和支持系统在解决变压器全生命周期成本计算问题方面具有可行性和有效性.

[1]陆爽,陈红兵,肖福利.资产全寿命周期管理在物资采购中的应用研究[J].华东电力,2010,38(9):1323-1326.
LU Shuang, CHEN Hong-bing, XIAO Fu-li. Research on application of life cycle asset management in materials procurement [J].East China Electric Power,2010,38(9):1323-1326.
[2] 帅国庆.电力企业资产全寿命周期管理:理论、方法及应用[M].北京:中国电力出版社,2010: 2045.
[3] 夏成军,邱桂华,黄冬燕,等.电力变压器全寿命周期成本模型及灵敏度分析[J]. 华东电力,2012,40(1):26-30.
XIA Cheng-jun,QIU Gui-hua,HUANG Dong-yan, et al. Life cycle cost model and sensitivity analysis of power transformer [J]. East China Electric Power,2012,40(1):26-30.
[4] 姜益民. 变压器的全寿命周期成本分析[J].上海电力,2004(3):188-191.
JIANG Yi-min. LCC assessment on transformer [J]. Shanghai Electric Power, 2004(3):188-191.
[5] 刘建强,钟立华,马仲能,等. 资产全寿命周期管理在变压器招评标中的应用[J]. 广东电力,2011, 24(3):17-20.
LIU Jian-qiang,ZHONG Li-hua,MA Zhong-neng, et al. Research on application of LCAM in bid invitation/evaluation of transformers [J]. GuangDong Electric Power, 2011, 24(3):1720.
[6] 孙鹏,陈绍辉,张彩庆. 基于全寿命周期成本模型的变电站设备最佳寿命周期评估[J].南方电网技术,2011(5):96-100.
SUN Peng, CHEN Shao-hui, ZHANG Cai-qing. LCC assessment on the best life cycle of substation equipment [J]. Southern Power System Technology, 2011(5):96-100.
[7] GREENE L F, SHAW B L. The steps for successful life cycle cost analysis [C]∥Proceeding of the IEEE 1990 National Aerospace and Electronics Conference. [S.l.]: IEEE, 1990: 1209-1216.
[8] DOWNING D J, MCCONNELL B W, BARNES P R, et al. Economic analysis of efficient distribution transformer trends [R].\
[S.l.\]:EPA,1998: 89-93.
[9] 陆广香. 最大负荷损耗小时数求取方法质疑 [ J/OL]. [2012-04-12]. http:∥wenku.baidu.com/view/2f16d2ef81c 758f5f61f67cc.html,1996,2.
LU Guang-xiang. Querying for maximum load loss hours calculating method [J/OL]. [2012-04-12].
http:∥wenku.baidu.com/view/ 2f16d2ef81c 758f5f61f67cc.html,1996,2.
[10] CUI Xin-qi,YIN Lai-bin, FAN Chun-ju, et al. Study of LCC for power transformer in modification of transformer substation [J]. Power System Protection and Control, 2010, 38(7):69-73.
[11] 韩天祥,黄华炜,陆一春.LCC管理技术在国外电力系统的研究与应用[J].上海电力,2004(3):192-194.
HAN Tian-xiang, HUANG Hua-wei, LU Yi-chun. LCC management technology research and application in foreign electric power system [J]. Shanghai Electric Power, 2004(3):192-194.
[12] 杜国付,李骥,赵铁城. 空调冷热源系统全寿命周期成本计算软件开发[J]. 建筑科学,2011(2): 21-25.
DU Guo-fu, LI Ji, ZHAO Tie-cheng. Software development of life cycle cost for heat/cold sources of air-conditioning system [J]. Building Science, 2011(2): 21-25.

[1] LIAO Zheng-wei, ZHANG Xue, YOU Wei, YAO Wei,LU Zheng-yu. Variable LLC circuit used in ultra-wide input voltage range[J]. J4, 2013, 47(12): 2073-2079.
[2] ZHENG Sheng, CAI Zhuo-jian, WANG You-sheng, QIAN Zhao-ming. Integrated driving circuit of IGBT series connected system[J]. J4, 2013, 47(12): 2094-2100.
[3] ZHU Ming-lei, ZHAO Rong-xiang. Parallel convertor system with high speed distributed master-slave control method[J]. J4, 2013, 47(11): 2031-2037.
[4] MENG Pei-pei, ZHANG Jun-ming, QIAN Zhao-ming. Modeling and predicting for common mode noise in Boost converter[J]. J4, 2012, 46(10): 1851-1856.
[5] MENG Pei-pei, ZHANG Jun-ming, CHEN Heng-lin, QIAN Zhao-ming. Modeling and predicting for common mode noise
disturbance in Flyback converter
[J]. J4, 2012, 46(9): 1702-1707.
[6] DING Jia-feng, LUO An,HU Zhi-kun,WANG Hui-hai,CAO Jian. Detection characteristic of gases of solid oxide fuel cell[J]. J4, 2012, 46(6): 1008-1013.
[7] WANG Shi-tao, ZHANG Da-min, LU Zheng-yu, ZHANG De-hua. Current-source thyristor rectifier controller with
fast current response
[J]. J4, 2012, 46(2): 189-193.
[8] GE Jun-xu, LI Xin, TONG Shui-guang,WU De-zhong, TIAN Zhi-gang, WANG Peng. Grid control strategy of wind turbine based on
double voltage source rectifier
[J]. J4, 2011, 45(3): 480-485.
[9] RONG Ping, CHEN Wei, DENG Zhe, GU Yi-lei, LU Zheng-yu. Variable topology converter dedicated to wide input range applications[J]. J4, 2011, 45(3): 472-479.
[10] CHEN Wei, LV Zheng-Yu. Novel soft-switching push-pull type LLC resonant converter and
its topology investigation
[J]. J4, 2010, 44(8): 1540-1547.
[11] HU Zhi-Kun, WANG Mei-Ling, GUI Wei-Hua, YANG Chun-Hua, DING Jia-Feng. Support vector machine based classification method for
timeseries periodic waveform
[J]. J4, 2010, 44(7): 1327-1332.
[12] CHEN Wei, LV Zheng-Yu. Novel soft switching resonant reset wide input range dual switch
forward converter
[J]. J4, 2010, 44(5): 1025-1031.
[13] GU Yi-Lei, CHEN Wei, LV Zheng-Yu. Flexible converter and its applications[J]. J4, 2010, 44(3): 521-527.
[14] LIU Jun, DAN Jian-Jiang, ZHANG Zhong-Chao, HE Xiang-Ning. Application of parallel resonant converter operating in  discontinuous current mode[J]. J4, 2010, 44(3): 516-520.