机械与能源工程 |
|
|
|
|
基于盾构密封舱压力直接反馈地表变形控制 |
王林涛,龚国芳,施虎,刘怀印 |
浙江大学 流体动力与机电系统国家重点实验室,浙江 杭州 310027 |
|
Ground surface deformation control based on chamber
pressure direct feedback |
WANG Lin-tao, GONG Guo-fang, SHI Hu, LIU Huai-yin |
State Key Laboratory of Fluid Power Transmission and Control, Zhejiang University, Hangzhou 310027, China |
引用本文:
王林涛,龚国芳,施虎,刘怀印. 基于盾构密封舱压力直接反馈地表变形控制[J]. J4, 2012, 46(7): 1182-1188.
WANG Lin-tao, GONG Guo-fang, SHI Hu, LIU Huai-yin. Ground surface deformation control based on chamber
pressure direct feedback. J4, 2012, 46(7): 1182-1188.
链接本文:
http://www.zjujournals.com/eng/CN/10.3785/j.issn.1008-973X.2012.07.005
或
http://www.zjujournals.com/eng/CN/Y2012/V46/I7/1182
|
[1] 刘仁鹏.土压平衡盾构技术综述[J] .现代隧道技术,2000(1):1-7.
LIU Renpeng. Review of earth pressure balance shield [J]. Modern Tunneling Technology, 2000(1): 1-7.
[2] SUCHATVEE S, HERBERT H E. Artificial neural networks for predicting the maximum surface settlement caused by EPB shield tunneling [J]. Tunneling and Underground Space Technology, 2006, 21(2): 133-150.
[3] 周江天.盾构隧道下穿铁路枢纽的风险和沉降控制技术[J]. 特种结构, 2010, 27(4): 7-10.
ZHOU Jiangtian. Risk and displacement prevention technology of shield tunnel going under through the railway terminal [J]. Special Structures, 2010, 27(4): 7-10.
[4] 张冬梅,黄宏伟,王箭明. 盾构推进引起地面沉降的粘弹性分析[J]. 岩土力学,2001, 22(3): 311-314.
ZHANG Dongmei, HUANG Hongwei, WANG Jianming. The viscoelastic analysis of the settlement of the soil above the tunnel caused by shield tunneling [J]. Rock and Soil Mechanics, 2001, 22(3): 311-314.
[5] 胡国良,龚国芳,杨华勇. 盾构掘进机土压平衡的实现[J].浙江大学学报:工学版,2006,40(5):874-877.
HU Guoliang, GONG Guofang, YANG Huayong. Realization of earth pressure balance for shield tunnelling machine [J]. Journal of Zhejiang University: Engineering Science, 2006, 40(5): 874-877.
[6] 徐前卫,朱合华,廖少明, 等. 均匀软质地层条件下土平衡盾构施工的合理顶进推力分析[J]. 岩土工程学报, 2008, 30(1): 79-85.
XU Qianwei, ZHU Hehua,LIAO Shaoming, et al. Analysis of reasonable thrust force during tunnel excavation in homogeneous soft ground by use of earth pressure balance shield machine [J]. Chinese Journal of Geotechnical Engineering, 2008, 30(1): 79-85.
[7] WANG Lintao, GONG Guofang, SHI Hu, et al. Rotation and gate movement compound control of screw conveyor hydraulic system with disturbance compensation [J]. Lecture Notes in Computer Science, 2010, 6424: 329-340.
[8] 刘东亮. EPB盾构掘进的土压控制[J]. 铁道工程学报,2005, 4(2): 45-50.
LIU Dongliang. Earth pressure balance control for EPB shield tunneling [J]. Journal of Railway Engineering Society, 2005, 4(2): 45-50.
[9] 邢彤,龚国芳,杨华勇. 盾构刀盘驱动扭矩计算模型及实验研究[J]. 浙江大学学报: 工学版, 2009, 43(10): 1794-1800.
XING Tong, GONG Guofang, YANG Huayong. Torque calculation of cutting head in shield machine and experimental study [J]. Journal of Zhejiang University: Engineering Science, 2009, 43(10): 1794-1800.
[10] 陈馈. 盾构施工技术[M]. 北京:人民交通出版社,2009: 40-63.
[11] 魏康林. 土压平衡盾构施工中泡沫和膨润土改良土体的微观机理分析[J]. 现代隧道技术, 2007, 44(1): 73-77.
WEI Kanglin. Micromechanism analysis for the soil improvement by foam and bentonite in EPB shield tunneling [J]. Modern Tunneling Technology, 2007, 44(1):73-77.
[12] NOMOTO T, IMAURA S, HAGIWARA T, et al. Shield tunnel construction in centrifuge [J]. Autom Construction, 1997, 5(5): 421-426.
[13] 施虎,龚国芳,杨华勇, 等. 盾构掘进土压平衡控制模型[J]. 煤炭学报, 2008, 33(3): 343-346.
SHI Hu, GONG Guofang, YANG Huayong, et al. Control model of earth pressure balance for shield tunneling [J]. Journal of China Coal Society, 2008, 33(3): 343-346.
[14] 施虎,龚国芳,杨华勇,等. 盾构掘进机推进力计算模型[J]. 浙江大学学报: 工学版, 2011,45(1): 126-131.
SHI Hu, GONG Guofang, YANG Huayong, et al. Determination of thrust force for shield tunneling machine [J]. Journal of Zhejiang University: Engineering Science, 2011, 45(1): 126-131.
[15] YANG Huayong, SHI Hu, GONG Guofang, et al. Earth pressure balance control for EPB shield [J]. Science in China Series E:Technological Sciences, 2009, 52(10): 2840-2848.
[16] 胡国良,龚国芳,杨华勇. 土压平衡式盾构机土压控制的模拟实验[J]. 液压与气动,2007 (9): 1-3.
HU Guoliang, GONG Guofang, YANG Huayong. Simulating experiment of earth pressure control for EPB shield [J]. Chinese Hydraulics and Pneumatics, 2007 (9): 1-3.
[17] 胡国良. 盾构模拟试验台电液控制系统关键技术研究[D]. 杭州: 浙江大学,2006.
HU Guoliang. Research into electrohydraulic control system for a simulator test rig of shield tunneling machine [D]. Hangzhou: Zhejiang University, 2006. |
|
Viewed |
|
|
|
Full text
|
|
|
|
|
Abstract
|
|
|
|
|
Cited |
|
|
|
|
|
Shared |
|
|
|
|
|
Discussed |
|
|
|
|