非对称超载对地铁深基坑的支撑不动点调整系数影响
林舒琦,范晓真,徐长节,方焘

Impact of asymmetric overload on fixed-point adjustment coefficient of strut in deep metro excavation
Shuqi LIN,Xiaozhen FAN,Changjie XU,Tao FANG
表 3 民治站基坑支撑不动点调整系数计算值、实测值与设计采用值对比
Tab.3 Comparison of calculated value, measured value and design adopted value of fixed-point adjustment coefficient for foundation pit support of Minzhi Station
超载工况h/HΔl_mΔs_mλld[6]λl_cλl_mΔλlξl/%λsd[6]λs_cλs_mΔλsξs/%
不同超载大小0.61540.65.50.5~1.00.8290.8820.0536.390~0.50.1710.1180.05330.99
不同超载大小0.77638.011.10.5~1.00.7670.7740.0070.910~0.50.2330.2260.0073.00
不同超载作用宽度0.61540.65.50.5~1.00.8390.8820.0435.130~0.50.1610.1180.04326.71
不同超载作用宽度0.77638.011.10.5~1.00.7740.7740.0000.000~0.50.2260.2260.0000.00
不同超载与坑边距离0.61540.65.50.5~1.00.7990.8820.08310.390~0.50.2010.1180.08341.29
不同超载与坑边距离0.77638.011.10.5~1.00.7280.7740.0466.320~0.50.2720.2260.04616.91