基于系统动力学的装配式建筑项目进度分析与系统实现
李昊翔,侯公羽,陈钦煌,王丹丹,邵耀华,陶志刚

Analysis and system implementation for prefabricated construction project schedule based on system dynamics
Haoxiang LI,Gongyu HOU,Qinhuang CHEN,Dandan WANG,Yaohua SHAO,Zhigang TAO
表 7 SM-A1模块的计算结果
Tab.7 Calculation results of SM-A1 module
代码名称ES/dEF/dLS/dLF/dFF/dTF/d
A基础工程01001000
B主体吊装71871800
DJGD管安装及开孔929113102
F消防管线安装1030163606
G箱体拼接缝防水82892901
C屋面安装13283146018
H地面拼缝72272200
L舾装板墙体安装2232263604
I砂浆找平1723243007
J门窗梁焊接1821273009
K门窗安装2128303729
Q现场轻钢龙骨隔墙82982900
T卫生间防水(含蹲便池)2938324103
N自流平3036374307
OPVC地胶铺设3339404607
U卫生间地面3241354403
V卫生间墙面饰面3541384403
W卫生间隔断3743404603
R楼梯间隔墙面层2935384409
S楼梯间地面瓷砖3137404609
X强弱电间地面瓷砖2931293100
E强弱电布线934113602
M天花安装3443364502
P灯具安装3444364602
Z电气设备安装2545264601
Y外饰面安装调平3146314600
Aa收尾调试4651465100