计及高背压改造机组动态特性的厂级负荷分配
章艳,李佳丽,张莹,苏子航,陈筑,韩旭,吕泉

Plant-level load distribution considering dynamic characteristics of high back-pressure retrofit unit
Yan ZHANG,Jiali LI,Ying ZHANG,Zihang SU,Zhu CHEN,Xu HAN,Quan LV
表 3 高背压机组设计值和仿真结果比较
Tab.3 Comparison between design values and simulation results of high back-pressure unit
机组工况qm/(t·h−1)e1/%θ/℃e2/%
试验值仿真值试验值仿真值
240 MW
高背压工况
877.451862.022−1.7674.974.7080.03
165 MW
高背压工况
597.345595.417−0.3268.067.939−0.27
110 MW
高背压工况
400.641394.697−1.4861.861.768−0.20